Application:
As demonstrated through the construction of Harmony
Block at the Ma On Shan Phase II site in 1994, Shui
On was the first main contractor on Hong Kong Housing
Authority's Contractors' List to achieve a 6-day cycle
for the typical floor construction of Harmony Block
instead of the traditional 9-day cycle.
Description:
The 6-day cycle for typical floor construction of Harmony
Blocks was achieved by providing additional tower cranes,
wallforms, semi-precast slabs, close coordination and
good planning.
|