Application:
As demonstrated through the construction of Harmony Block at the Ma On Shan Phase II site in 1994, Shui On was the first main contractor on Hong Kong Housing Authority's Contractors' List to achieve a 6-day cycle for the typical floor construction of Harmony Block instead of the traditional 9-day cycle.

Description:
The 6-day cycle for typical floor construction of Harmony Blocks was achieved by providing additional tower cranes, wallforms, semi-precast slabs, close coordination and good planning.

 

 

Features and benefits:

  • Reduces the construction period for a 39-storey Harmony Block from 29 to 25 months.
  • Produces smooth slab soffit by adopting semi-precast planks and requires minimal timber formwork.
  • Shortens construction time without sacrificing the quality of housing units produced.